Y -- PLA Special Notice FY25 Joint Base Lewis McChord Multi Domain Task Force Buildings 3221-3222 SOL W912DW27RA017 DUE 10/08/2026 at 01:00PM -07:00 POC Cassandra Gonzalez, cassandra.p.gonzalez@usace.army.mil, tel:2065073218 Shawna West, shawna.west@usace.army.mil
USACE Seattle District has a requirement to convert two (2) existing barracks buildings into operational facilities for 3 tier levels of command. These buildings in general are referred as “the Hammer Heads”. The Hammer Handles have three (3) floors with a crawl space at grade elevation. The Hammer Heads are single floor. The Basement area with a main utility mechanical & electrical room extends partially under both the Hammer Head and the Hammer Handle.
The definitive removal / demolition work items for each building will require:
a) Hazardous material / debris abatement and removal mostly within the crawl space
b) Partial at ~ 75% removal / demolition of exterior building envelope, interior walls, etc.
c) Removal at ~ 90% removal of building mechanical – electrical systems
d) Removal of the existing roof EPDM system (but not the roof framing structure)
The definitive repair / new work items for each building will require:
e) New exterior envelope
f) New building mechanical – electrical systems
g) New Thermoplastic Polyolefin (TPO) Roof system
h) Painting of exteriors
Other considerations for site work coordination:
i) New utility connections (mostly by other entities)
j) Shared construction boundaries with adjacent current and future projects