99 -- Modernization of the Gillespie Field (SEE) Air Traffic Control Tower (ATCT) SOL 697DCK-27-R-SEE01 DUE 10/14/2026 at 05:00PM -04:00 POC Sam Culberth, Sam.G.Culberth@faa.gov
The FAA has a potential upcoming requirement for the modernization of the SEE ATCT, in El Cajon, CA. The FAA is seeking interested sources that are capable of completing this requirement. The disclosure of magnitude for this project is between $2,500,000 - $5,000,000, see attached Specifications and Drawings for full description of the work.
This market survey is being conducted in accordance with FAA Acquisition Management System (AMS) Policy section 3.2.1.2.1 Market Analysis. See attached market survey document to submit capability submittal/statement.
Please provide all capability submittals no later than 5:00pm ET, October 14, 2026.
Place of Performance: CA 92020 URL: https://sam.gov/opp/945b4d4755ec49ceb599c2fe803ea3df/view OutreachSystems Article Number: 20261003/PROCURE/0339